Capital Program Highlights

     
 
Current Six Year Program
2008-13
Six-Year
Program Cost
Major Construction Program Summary
BWI Marshall Airport Projects
New Construction
Comprehensive Signage Phase II $ 3.6 million
Airfield Pavement Improvement Phase I
Concourses D/E Ramp $ 15.0 million
Taxiways $ 19.6 million
Concourses C/D Ramp $ 56.8 million
Construction Closeout
Terminal A/B Expansion $ 3.6 million
Terminal Roadways and Skywalks $ 2.4 million
Daily Garage and Express Lot $ 1.9 million
Security
Baggage Screening Concourses D/E $ 35.8 million
Noise Zone and Protective Land Acquisition $ 11.6 million
Homeowner Soundproofing Assistance $ 5.3 million
BWI MARSHALL TOTAL $ 155.6 million
Regional Aviation Projects
Hagerstown Runway Extension $ 29.6 million
MAJOR PROGRAM TOTAL $ 185.2 million
Six-Year
Program Cost
Development & Evaluation Program Summary
BWI Marshall Airport Projects
Master Plan $ 7.4 million
Interim Airport Layout Plan Environmental $ 2.8 million
Planning & Preliminary Engineering
Terminal Modernization Program $ 3.9 million
Administrative Office Building $ 4.0 million
Runway Safety Area Improvements $ 6.0 million
BWI MARSHALL TOTAL $ 24.1 million
Martin State Airport Projects
New Air Traffic Control Tower $ 3.7 million
D&E PROGRAM TOTAL $ 27.8 million
Six-Year
Program Cost
System Preservation Minor Program Summary
Airport Technology (18 projects) $ 47.3 million
Airside Development (21 projects) $ 34.1 million
Annual Inspections (9 projects) $ 1.2 million
Comprehensive Planning & Design (30 projects) $ 113.3 million
Consolidated Rental Car Facility (3 projects) $ 3.1 million
Environmental Compliance (5 projects) $ 6.2 million
Equipment (6 projects) $ 10.4 million
Landside Development (20 projects) $ 13.9 million
Martin State Airport (14 projects) $ 31.8 million
Regional Aviation (7 projects) $ 13.2 million
Security Initiatives (15 projects) $ 24.1 million
Terminal Development (32 projects) $ 32.0 million
MINOR PROGRAM TOTAL $ 330.6 million